The long awaited Hockett Road realignment will be built |
On June 11 Goochland and VDOT held a location public hearing on the realignment of Hockett Road. Under discussion in various forms since at least 2013, the proposed road project will bisect the parcel of land at the end of Ashland Road south of Broad Street Road to connect with Hockett Road. A public hearing of design of the project is currently scheduled for September 8, 2025
The meeting presented three slightly different versions with
a roundabout where Hockett Road and the Ashland Road extension connect. There
will be no change to the signalized intersection of Broad Street and Hockett
Roads. The most likely scenario—as this was the first step in the lengthy and complicated
road building process and could change before construction begins not before
2028—shows a roundabout a bit north of Holly Lane with a stub into undeveloped
land on the west side of Hockett Road.
Road building is a complicated process. Long before a single
shovel full of dirt is moved, other factors must be addressed. These include acquisition
of rights of way; environmental concerns; civil rights; and design.
The proposed road is .5050 miles in length from Holly Lane to
Ashland Road. The projected cost is $17.6 million, which could change in the
next four years. Of that, the cost of engineering of roadway plans is estimated
at $1,568,000; right of way acquisitions, relocation assistance and utility
relocation $3,394,119; and construction $12,899,963.
Tom Kendrick, P.M., the preliminary engineering manager for VDOT,
explained that the proposed roundabout will be built with a turning radius to accommodate
large trucks and school buses without “rolling the kids around” as they negotiate
it.
He said that the roundabout will be designed to handle
current traffic and growth projected to 2040.
Speed limits in the roundabout will be 25 mph. Kendrick said
that extensive signage well before the roundabout will ensure that drivers do
not “sneak up on it”. Other warning devices would be pavement marking and
possibly lighting. (Please use that wonderful reflective paint that makes road
markings look like runway lighting at night with no need for electricity.)
Kendrick said that a traffic study about the appropriateness
of speed limits would be conducted after completion of the roundabout. There
were several comments that the current speed limit on Hockett Road, 55 mph, is
too fast. Congestion at the south end of Hockett, where it intersects with Rt 6,
was also mentioned, but that area is being addressed in another study.
The Hockett Road extension, said Kendrick, was expected to
be built long before now, but the economic downturn of the Great Recession
moved it to a back burner. Funding from federal, state, and local sources has
been secured. He contended that the pandemic changed land use patterns and the current
regional transportation (read roads) model is a “best guess” of what the future
will bring.
Kendrick said that he expects construction of the roundabout
will cause minimal traffic disruption as it will mostly occur at the side of Hockett
Road. There could be a weekend closure
to connect all the pieces near the end of construction. The rest of the extension
cuts through an open field and the stub for Ashland Road south of Broad Street
Road is already there and not expected to change.
Go to https://www.goochlandva.us/1254/Hockett-Rd-Realignment
for more details.
Send public comments about the project to Kendrick at Thomas.Kedrick@VDOT.Virginia. Gov
by June 22, 2024.
No comments:
Post a Comment