| Putting their heads together |
On the Friday afternoon before Christmas, Goochland
supervisors put their heads together for a capital improvement plan (CIP) workshop
to review capital needs for the county.
By FY2030, the county will need to fund at least $153,955,764
in capital projects. Of that total, $23,594,00 are utility projects, which are funded
by connection fees and operating budget.
During several meetings in 2025, the audit committee discussed
county financial policies established to ensure good stewardship of taxpayer
dollars. Thanks to the hard work of supervisors elected in 2011 and former
County Administrator Rebecca T. Dickson, Goochland earned three AAA bond
ratings, which enables it to borrow money at better than market rates to
finance capital projects, which include buildings and equipment with large
price tags and useful life longer than five years.
The supervisors decided to reduce the policy ratio of debt
to assessed valuation contending that the existing ratios were far more
conservative than neighboring jurisdictions and these funds should be put to
work. Exactly how that will be implemented is still to be determined.
County Administrator Dr. Jeremy Raley said the purpose of
the December 19 session was the continuation of conversations about high
profile capital assets and to gauge board sentiment about funding options going
forward. Departments presenting were public utilities, transportation, fire-rescue,
and updates about the space study and courthouse construction project. No decisions
were made.
(To view the entire information dense three-hour meeting, go
to the county website https://www.goochlandva.us/
click on “watch county meetings” and select BoS meeting December 19. Thanks to
Director of Information Technology Dan Stowers and his team for recording the
meeting and posting it online in a very timely manner.)
Utilities
Elizabeth McDonald, our new director of public utilities,
gave an overview of completed and ongoing DPU projects.
Working closely with Fire-Rescue, McDonald reported that all
52 “problematic” fire hydrants in need of repair or maintenance have been fixed
and no known fire hydrant issues remain in the system. She expressed the need for a formalized
hydrant maintenance program to identify problems and address them quickly.
McDonald reported that completed or almost finished DPU
projects, including a Plaza Drive waterline extension and replacement of the
force main from the eastern Goochland Pump Station have come in under budget. The
slightly more than $1 million budgeted for those projects will be returned to
the utility CIP budget.
Funded ongoing projects include the Sandy Hook Road water
loop, expected to improve reliability of water service in the Courthouse
Village area and support development along the Fairground Road extension. This
will not be started until the Fairground Road extension kicks off in 2027.
An “air stripping” system for the Courthouse Village elevated
water tank, with an estimated cost of $245K to reduce the EPA mandared levels
of trihalomethanes, a disinfectant by product that increases due to temperature
and water age, is needed as soon as possible. This requires installation of
equipment, which would take about a month to complete, said McDonald.
An upgrade to the Vally View Lane pump station and force
main in Courthouse Village to increase its capacity from the current 200
gallons per minute to 580 gpm to accommodate expected growth is also on the
list. The increase in pump size and force main velocity will also require increasing
pipe size from six to eight inches. The project, with an expected cost of
$1,681,000, can be funded over multiple fiscal years.
The Eastern Goochland Pump Station (on the north side of Rt.
6 just east of Tuckahoe Pines) pumps are nearing the end of their useful life,
said McDonald, and have started to require additional maintenance. For FY2027
she requested $150k for a condition assessment to determine the next best steps
to maintain pumping capacity.
Most of the EGPS, approximately 75 percent, capacity is used
by Henrico, which pays a pro rata portion of the cost. The facility has four pumps
but was built with slots for six to accommodate growth.
A proposed Rockville connection to the Henrico County water system
which will require approval from Henrico, would add a reliable and permanent
emergency water source for customers north of I64. It would also improve quality.
The total estimated cost of the project is $1 million. Talks with Henrico are
ongoing.
A Ridgefield Parkway booster pump station and ground storage
tank to support growth and fire flow has an estimated price tag of $16.768
million. This was identified in the 2015 utility master plan for 2035, but
development needs pulled it forward. Most public water in the east end of
Goochland comes from Henrico County through the Tuckahoe Creek Service
District, or other agreements.
A low-pressure sewage collection and conveyance system to
bring sewer service to about 75 properties along River Road West in Courthouse
Village, which can be phased over multiple years. The estimated cost is $4.5
million.
The West Creek River Road flow control project, to improve
water pressure in Lower Tuckahoe may not be needed as operational improvements
may have addressed the issue. McDonald asked residents in this area that are
still experiencing pressure issues to contact DPU at 804-556-5835.
In summary, DPU capital requests total $520k for FY27, and
$14,223,000 for FY28. Utilities are funded by connection fees and customer
service charges.
Early next year, said McDonald, DPU staff will present the
updated utility master plan.
Roads
County Engineer Austin Goyne said that a new website: https://goochlandva.us/roads contains consolidated information about all county
transportation projects.
The Ashland Road/I64 interchange improvements are moving
along with completion expected in August of 2029. Extending Fairground Road to
Rt. 6 in Courthouse Village will get underway in 2027 with expected completion
also in 2029.
Bids for the roundabout at the Oilville Road/westbound I-64
off ramp to mitigate treacherous evening rush conditions there will be
solicited early in 2026 with completion expected in September 2027. Acquisition
of rights of way for a roundabout at the intersection of Fairground and Maidens
Road are scheduled to begin in November 2028, with completion anticipated for
August of 2030.
Other current projects also include sidewalk plans for
Courthouse Village between Goochland Cares and Reed Marsh. Goyne said that
current assumptions use a VDOT template that anticipates completion at the end
of 2029 is “extremely conservative.” He said that “staff and our consultant
will work diligently to deliver the project well ahead of schedule.”
The realignment of Hockett Road to connect with Ashland Road
at Broad Street Road is chugging along. First mentioned around 2013, a new
proposed route, placing a roundabout in front of the VRCC Vet Emergency Clinic,
which avoids flood plain and creek impacts that complicated the previous plan
has been proposed. Completion could be as early as 2029. There will be a public
hearing on the new alignment on January 13 at 5:30 p.m. at Dover Church on Manakin
Road.
Looking ahead, solutions to the Ashland/Rockville Road interchange
are being investigated.
Goochland, like most Virginia localities, is dependent on
VDOT for road construction and maintenance. Roads are paid for through a
complicated, almost byzantine process involving different subagencies and
regional authorities and competing with other jurisdictions for projects with
regional impacts.
Goyne said that establishing better lines of communication between
Goochland and VDOT improves outcomes. He cited early completion of the Sandy
Hook/Fairground Road roundabout as an example.
Improvements to Rt. 288 are also in the works.
District 2 Supervisor Neil Spoonhower, along with Goyne and
Transportation Manager Patrick Longerbeam, represents the county on the Central
Virginia Transportation Authority (CVTA) https://cvtava.org/.
Spoonhower pointed out that these road projects, whose cost is estimated around
$76 million, are funded mostly through grants, awards, and VDOT money, not the
county general fund. Thanks to Goyne’s focus
on securing various funding mechanisms, Goochland has secured a total of $200
million to pay for these road improvements. Spoonhower, who also works to
leverage regional transportation partnerships to the county’s advantage, contended
that over five years, Goochland will receive about $200 million in
transportation funding, which is an excellent return on the $20 million we generate
in sales and gas tax.
Emergency Communications
Major Mike East of the Goochland County Sheriff’s Office explained
the need for a new communications tower in the northeast sector of the county. Deputies,
fire-rescue providers, animal control, and dispatchers must be able to talk to
each other and neighboring agencies.
Currently, the county has five towers and uses a conventional
radio system installed in 2017, which, said East, makes it something of a
dinosaur tech wise. Handheld radios can communicate with radio towers from 6-10
miles away depending on topography, weather, structure density, and tower
height.
Last summer the Creekmore tower, went “down” creating a dead
zone for handheld radios in the east end. Vehicle radios were not impacted, but incident
response is often on foot. A “mayday” call from a firefighter injured inside a
burning structure, or an “officer down” call on a handheld radio could not reach
dispatch to summon help.
Another tower would add redundancy to the system.
East said that the GCSO is also investigating a transition
to a “trunking” system, which will improve communications with neighboring
jurisdictions. Goochland, said East, is currently “on an island” when communicating
with our partners in other counties.
The estimate cost for the tower, including land acquisition,
is $4.245 million in a FY28 timeframe.
Fire-Rescue
D. E. “Eddie” Ferguson, Jr. Chief of Fire-Rescue and
Emergency Management focused his presentation on apparatus, ambulances, engines,
and tankers. The fire-rescue fleet has the potential to have eight engines in
service, six of which, one for each exiting station, are primary, the others
reserve.
Last month, while responding to a call on the Rt. 288 bridge
over the James River, an engine was hit by a drunk driver, totaling the
vehicle. Thankfully, no lives were lost. Insurance on the loss was $194,750.
The other reserve engine is being repaired, leaving the county with no reserve engines.
This, said Ferguson, is not a unique situation.
As most of the county is not served by public water, tankers
are needed to transport water to fires. Some tankers in the fleet date back to 2002
have high mileage and can be expensive to repair.
Engines, tankers, and ambulances are not only expensive, but
have very long delivery lead times, up to four years. Ferguson said that apparatus
prices are estimated to increase 12 percent per year.
Ferguson presented two scenarios for apparatus procurement.
One, order multiple units early to arrive in the same year that funding is
allocated, which he contended would save $786,838. The other is to order units
in the same budget year that funding becomes available, costing $786,838 more. Ordering
ahead could lock in current pricing.
Construction on Station 8 on Whitehall Road has been put out
to bid, which closes next month. Architectural and engineering for Station 7 on
Hockett Road may be put out to bid early next year.
A study of county space needs is in progress. Discussions
about the new circuit courthouse are also ongoing.
An addition to the high school to accommodate Goochland’s exceptional
career and technical education (CTE) program has a placeholder of $20 million
but was mentioned only in passing as the supervisors wondered if this number should
be increased.
Funding
Among funding options for CIP are cash proffers, paid by developers,
to offset certain capital needs resulting from growth. These include schools, fire-rescue,
roads, parks, and libraries. Proffers have generated a total of $8,410.579, but
must be allocated by category, and in some cases, geographically.
General obligation bonds, whose $96 million issue was overwhelmingly
approved in a 2021 referendum are a potential funding source. Some were issued
in 2022; the remainder could cover public safety projects. Financing could be obtained
through the Virginia Resources Authority.
County financial policy limits debt service to 12 percent of
general fund expenditures with a target of 10 percent. Existing debt service is
about five percent. Adding $101,500,000 in debt financed projects is estimated
to hit 10 percent in FY29 and 30, easing a bit thereafter.
No decisions were made at the meeting, but the board clearly
learned a lot and has a lot to ponder over the holiday break. May they find the
wisdom to fund these capital needs in a fiscally responsible manner.
No comments:
Post a Comment