Proposed diverging diamond interchange (Goochland County image) |
Spring town hall meetings.
The schedule for Goochland Spring town hall meetings is as
follows: District 1, Monday, March 24 at Byrd Elementary School, 2704
Hadensville Fife Road; Districts 2 and 3 Monday, March 31 at the county
administration building1800 Sandy Hook Road in Courthouse Village; Districts 4
and 5 Thursday, March 27 at the Residence Inn at the Notch, 800 Wilkes Ridge
Circle, roughly opposite the Wawa on Broad Street Road in Centerville. All
meetings will start at 6 p.m.
Supervisors and school board members for their respective
districts will attend and answer questions.
Meetings will be livestreamed at https://va-goochlandcounty.civicplus.com/1154.
Submit questions to townhall@goochlandva.us.
Diverging Diamond and other road delights
Phillip Frazier, Assistant Resident Engineer in the VDOT
Ashland Residency, presented an update on the diverging diamond planned for the
I-64 Ashland Road interchange. In December, Frazier reported, VDOT received conditional
approval from the Federal Highway Administration, essentially a “thumbs up” for
the diverging diamond project. This will include the construction of a second
bridge over the interstate, parallel to the existing span.
The project has transitioned from a traditional design bid
build project to a design build project, which will allow the project to be
delivered about a year earlier than first anticipated, said Frazier. This will give
the design build team selected to complete the project flexibility to be creative
and innovative during construction, which could lead to shaving about a year
off the project’s completion date.
VDOT will complete about the first third of the project
design then pause and solicit bids for the final design team. When the contract
is awarded, the project will be turned over to that design build team for
completion, which will be responsible for acquiring rights of way and
relocating utilities, explained Frazier.
Additionally, the Hickory Haven Park and Ride relocation
will be “bundled” into the project to avoid different contractors working in
close proximity “stepping on each other’s toes” during construction. This will
delay the completion of the park and ride, on the west side of Ashland Road,
just south of I64, whose design is currently nearing the right-of-way acquisition
phase.
The park and ride relocation is fully funded. The diverging
diamond, estimated to cost $79 million, has about $76 million in dedicated
funding. Frazier said that options are being explored to close the gap by
refining estimates to get it within budget. He said that VDOT will exhaust all
options to secure state funding before coming back to Goochland for the shortfall
but wanted the supervisors to be aware of the issue.
There was a question about improving access to Bennington
Road, which runs roughly parallel to I64 and intersects with Ashland Road north
of the interstate. Frazier said that the project now includes the realignment
of Bennington Road, moving its intersection on the east side of Ashland Road further
north, to ease access for the businesses currently on Bennington Road, and
perhaps attract more commercial development to that area.
This increased cost projections as the water line that needs
to be moved to accommodate the improvement turned out to be a 16 rather than eight-inch
line as specified in the preliminary estimates.
Preliminary drawings for a temporary traffic signal, to
manage traffic during construction of Project Rocky, the Amazon distribution center,
was received by the VDOT traffic engineering group last week, said Frazier.
This is well ahead of the initial six to nine months estimate for installation
of this signal.
Frazier said that the timeline for completion of the
diverging diamond interchange will become more precise when it has been scoped,
which will lock in the cost estimate and schedule. This cannot happen until
completion of the National Environmental Protection Agency (NEPA) documents,
after which a public hearing will be held, perhaps in late summer. Then the
procurement process will begin with requests for qualifications, request for
proposals, and an award date of September 2026. Frazier estimated a three-year construction
window with completion in August 2029, which is about a year sooner than
earlier estimates.
Neil Spoonhower, District 2, said that the supervisors made
a commitment when approving Project Rocky in 2022 to deliver it with minimal
negative impacts to the county.
“We are working very hard and going in the right direction.
Hopefully, we’ll be able to continue on that trend to get this intersection,
which will be a great corridor adding value to the county, built out,”
Spoonhower said.
TCSD addition
During evening public hearings, the supervisors voted unanimously
to add four parcels of land on the west side of Ashland Road owned by Amazon
Services, LLC, known as Project Rocky, to the Tuckahoe Creek Service District.
The project needs public water and sewer to operate, but, according to Wayne Stephens,
interim director of the Goochland Department of Public Utilities, will use a relatively
small amount of capacity. Project Rocky will pay ad valorem tax levied on all
land in the TCSD thar services the debt Goochland County incurred when the
district was created in 2002.
During the public hearing, a resident asked about the costs
and financial implications of Project Rocky to Goochland County.
No comments:
Post a Comment